Hi Gerry Hodgins,
Thanks for your input. I have gone through the OSS notes 787744 but still I am some question.
In Project results analysis of a project/wbs I am using the category P (Costs of Complaints and Commissions) in configuration step Define Update for Results Analysis. I have created separate line id for complaints and commissions and linked with category P with separate secondary cost element (31) COS/Revenue and Reserve.
We are using manual planning in project and I do have a separate primary cost element for complaints and commission.
I have total plan cost including complaints and commissions let say 272000 and out of which 12000 is belong to complaints and commissions.
When I run results analysis the plan value is not updating plan value for complaints and commission is not updating in plan cost commission / complaint. ( see below image). My requirement is to update plan value in plan cost commission / complaint field in total box of below result of RA run and also I have requirement to calculate reserve based of completion percentage.
Please suggest me how the plan cost form commission / complaint will get plan cost in this run ( will the OSS notes 787744 will help me for this purpose.
Aniket